Yaupon Solar SLF
204.08 MW generation in Milam, TX · In queue since March 2021 · Proposed COD July 2027
204.08 MW
Capacity
1
Components
Solar
5y 2m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
2y 6m
IA → COD
3y 10m
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-01
Yaupon Solar SLF is a proposed 204.08 MW solar generation project located in Milam County, Texas. The project, developed by Yaupon Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0042, with a queue entry date of March 30, 2021. The proposed commercial operation date is July 1, 2027.
The project's Interconnection Agreement (IA) has been executed as of September 28, 2023. The point of interconnection is Tap 345 kV Gibson Switch (3706) _x0013_ TNP One (39950).
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Yaupon Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Gibson Switch (3706) _x0013_ TNP One (39950)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Yaupon Solar SLF