Pradera Solar
118 MW generation in Webb, TX · In queue since July 2021 · Proposed COD March 2027
118 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
Pradera Solar is a proposed 118 MW solar generation project located in Webb County, Texas. The project, developed by Pradera Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0056, with a queue entry date of July 8, 2021. The proposed commercial operation date is March 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the tap 345 kV Lobo (80219) - Fowlerton (5709).
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pradera Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV Lobo (80219) - Fowlerton (5709)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.