Briggs Storage
70.39 MW storage in Haskell, TX · In queue since May 2021 · Proposed COD April 2028
70.39 MW
Capacity
1
Components
Battery
5 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-15
Briggs Storage is a proposed 70.39 MW battery storage project in Haskell County, Texas. The project, developed by Briggs Solar, LLC, is located within the ERCOT region and consists entirely of battery storage. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0058, with a queue entry date of May 31, 2021, and a proposed commercial operation date of April 15, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project's point of interconnection (POI) is on the tap 345kV 60515 Clear Crossing - 60507 Pendulo line. Briggs Storage has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Briggs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 60515 Clear Crossing - 60507 Pendulo
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AZURE_RN
- POI Substation
- Clear Crossing Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14