Eighteenmile Solar SLF
153.06 MW generation in Goliad, TX · In queue since August 2021 · Proposed COD December 2026
153.06 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Eighteenmile Solar SLF is a proposed 153.06 MW solar generation project located in Goliad County, Texas. The project, developed by Weser Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0061, with a queue entry date of August 18, 2021. The proposed commercial operation date is December 1, 2026, and the project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 153.06 MW of solar photovoltaic generation. The point of interconnection is Tap 138kV 5730 Four Corners - 5728 Choate. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Weser Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5730 Four Corners - 5728 Choate
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- RAYB_G78910
- POI Substation
- Four Corners Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.