Triple B Solar Alt#2
150 MW generation in Lampasas, TX · In queue since June 2021 · Proposed COD July 2027
150 MW
Capacity
1
Components
Solar
4y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
Triple B Solar Alt#2 is a proposed 150 MW solar generation project located in Lampasas County, Texas. The project, developed by Triple B Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0069. It entered the interconnection queue on June 10, 2021, and has a proposed commercial operation date of July 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 150 MW of solar capacity. It is listed as active in the interconnection queue and has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Lampasas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Triple B Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 7066 Adamsville - 7064 Lampasas
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Adamsville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.