Sypert Branch Solar Project

ERCOT-24INR0070BetaActiveSolarERCOTLBNL + Live

261.15 MW generation in Milam, TX · In queue since September 2021 · Proposed COD April 2026

261.15 MW

Capacity

1

Components

Solar

4y 8m

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection

Queue → IA

2y 1m

IA → COD

2y 6m

Total Duration

2y 1m

Schedule

0 months past proposed COD

Construction75%
Queue EntrySep 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-30

About

The Sypert Branch Solar Project is a proposed solar generation project located in Milam County, Texas, with a total capacity of 261.15 MW. Developed by Sypert Branch Solar LLC, the project consists entirely of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0070, with a queue entry date of September 21, 2021, and a proposed commercial operation date of April 30, 2026.

The project's interconnection agreement has been executed as of October 12, 2023. The point of interconnection is Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2. The Sypert Branch Solar Project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sypert Branch Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Sypert Branch Solar Project