Apogee Wind II
47.25 MW generation in Throckmorton, TX · In queue since July 2021 · Proposed COD March 2027
47.25 MW
Capacity
1
Components
Wind
4y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
The Apogee Wind II project is a proposed wind generation facility with a total capacity of 47.25 MW. It is located in Throckmorton County, Texas, and is being developed by King Creek Wind Farm 3, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-24INR0078, with an interconnection queue entry date of July 13, 2021.
The proposed commercial operation date for Apogee Wind II is March 31, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 60791 Perigee Substation at 345kV.
Generated from interconnection queue and public data sources
State
TX
County
Throckmorton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
King Creek Wind Farm 3, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60791 Perigee Substation 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Apogee Wind II