251.3 MW generation in Ellis, TX · In queue since July 2021 · Proposed COD September 2027
251.3 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
Boxcar Solar 2 is a proposed solar generation project with a total capacity of 251.3 MW, located in Ellis County, Texas. The project is being developed by EDF Renewables Development, Inc. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0079, with a queue entry date of July 13, 2021. The proposed commercial operation date is September 30, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Boxcar Solar 2 is the Tap 345 kV 1907 Venus N - 68091 Navarro. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1907 Venus N - 68091 Navarro
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DSWL_BES1
- POI Substation
- Venus Substation