Pisgah Ridge Solar 2
101.89 MW generation in Navarro, TX · In queue since July 2021 · Proposed COD December 2028
101.89 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Pisgah Ridge Solar 2 is a proposed solar generation project located in Navarro County, Texas, within the ERCOT region. The project, developed by Pisgah Ridge Solar 2, LLC, has a total capacity of 101.89 MW. It consists solely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0086, with an original queue entry date of July 14, 2021. The proposed commercial operation date is December 1, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 68091 Navarro - 46020 Limestone. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pisgah Ridge Solar 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Navarro Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pisgah Ridge Solar 2