Pisgah Ridge Storage 3
101.36 MW storage in Navarro, TX · In queue since July 2021 · Proposed COD December 2028
101.36 MW
Capacity
1
Components
Battery
4y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Pisgah Ridge Storage 3 project is a proposed 101.36 MW battery storage project located in Navarro County, Texas. Developed by Pisgah Ridge 3, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0087, with a queue entry date of July 14, 2021. The proposed commercial operation date is December 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 68091 Navarro - 46020 Limestone.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pisgah Ridge 3, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Navarro Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pisgah Ridge Storage 3