BRP Springbok Solar
202.39 MW generation in Hale, TX · In queue since August 2021 · Proposed COD December 2027
202.39 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Springbok Solar project is a proposed 202.39 MW solar generation facility located in Hale County, Texas. Developed by Antelope Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0091, with a queue entry date of August 25, 2021. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 23920 Blackwater Draw Switching Station at 345kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Hale
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Antelope Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23920 Blackwater Draw Switching Station 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Blackwater HVDC Tie
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BRP Springbok Solar