Oriana Solar
181 MW generation in Victoria, TX · In queue since August 2021 · Proposed COD April 2025
181 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
1y 6m
IA → COD
2y 2m
Total Duration
1y 6m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-04-06
Oriana Solar is a proposed 181 MW solar generation project located in Victoria County, Texas. The developer is Oriana Solar LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0093, with a queue entry date of August 25, 2021, and a proposed commercial operation date of April 6, 2025. The interconnection agreement (IA) has been executed as of February 27, 2023.
The proposed project is linked to the existing Oriana Solar LLC operating plant (EIA plant ID 65849). The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oriana Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5502 Rayburn - 5584 Vanderbilt
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ORIANA_RN
- POI Substation
- Highlands Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesNo ask pi reports yet for this entity.