BRP Volga BESS
174.63 MW storage in Dallas, TX · In queue since December 2021 · Proposed COD December 2027
174.63 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The BRP Volga BESS project is a proposed 174.63 MW battery storage project located in Dallas County, Texas. Developed by BRP Volga BESS LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0096, with a queue entry date of December 20, 2021, and a proposed commercial operation date of December 1, 2027. The project's interconnection point is the 138 kV Seagoville Switch Substation. Its interconnection status is currently in the Facility Study phase.
The proposed project is a standalone storage facility, with all 174.63 MW of capacity coming from battery technology.
Generated from interconnection queue and public data sources
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Volga BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Seagoville Switch Substation (#2434; ONCOR)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Seagoville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BRP Volga BESS