Two Rivers Solar
219.35 MW generation in Milam, TX · In queue since July 2021 · Proposed COD June 2029
219.35 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-07
Two Rivers Solar is a proposed solar generation project located in Milam County, Texas, with a total capacity of 219.35 MW. Developed by Two Rivers Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0099, with a queue entry date of July 27, 2021. The proposed commercial operation date is June 7, 2029, and the interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing Two Rivers Solar operating plant (EIA plant ID 68198). The Two Rivers Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Rivers Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 64 Milano _x0013_ 32 Robertson
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Branchville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26