Lampe Solar
60.24 MW generation in Washington, TX · In queue since August 2021 · Proposed COD December 2027
60.24 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-26
The proposed Lampe Solar project is a 60.24 MW solar generation facility located in Washington County, Texas. Developed by Gransolar Texas Seven LLC, the project consists of 60.24 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0101, with a queue entry date of August 3, 2021, and a proposed commercial operation date of December 26, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Lampe Solar operating plant (EIA ID 67781). Recent news coverage has discussed the project in the context of industry developments.
Generated from interconnection queue and public data sources
State
TX
County
Washington
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Seven LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 7572 Gay Hill - 7573 Lyons
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Gay Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lampe Solar