Opuntia Solar SLF
102.04 MW generation in Refugio, TX · In queue since August 2021 · Proposed COD March 2028
102.04 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-10
Opuntia Solar SLF is a proposed solar generation project with a total capacity of 102.04 MW. The project, located in Refugio County, Texas, is being developed by Opuntia Solar, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0103, with a queue entry date of August 24, 2021.
The proposed commercial operation date for Opuntia Solar SLF is March 10, 2028. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is tap 138kV 5607 Warburton - 8912 Medio Creek.
Generated from interconnection queue and public data sources
State
TX
County
Refugio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Opuntia Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 5607 Warburton - 8912 Medio Creek
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Warburton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.