Kildare (ERCOT-24INR0110) — Project Summary

Queue ID
ERCOT-24INR0110
Capacity
70 MW
Technology
Solar
Status
active
Location
Jackson, TX
Region
ERCOT
Developer
Galsol, LLC
IA Status
Facility Study

Kildare

ERCOT-24INR0110BetaActiveSolarERCOTLBNL + Live

70 MW generation in Jackson, TX · In queue since January 2022 · Proposed COD September 2026

70 MW

Capacity

1

Components

Solar

4y 4m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

4y 8m

Facilities Study50%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-30

About

The Kildare project is a proposed 70 MW solar generation project located in Jackson County, Texas. Developed by Galsol, LLC, the project entered the ERCOT interconnection queue as ERCOT-24INR0110 on January 28, 2022. The proposed commercial operation date is September 30, 2026, and the project's interconnection status is currently in the Facility Study phase.

The project consists of 70 MW of solar photovoltaic generation. The point of interconnection is the 5524 Cordele 69 Sub 69 kV. The Kildare project is currently listed as active within the ERCOT interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Jackson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Galsol, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

5524 Cordele 69 Sub 69 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MUSTNGCK_ALL
POI Substation
Cordele Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Kildare