Aster Solar
203.52 MW generation in Guadalupe, TX · In queue since September 2021 · Proposed COD June 2029
203.52 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Aster Solar is a proposed 203.52 MW solar generation project located in Guadalupe County, Texas. The project, developed by Aster Solar, entered the ERCOT interconnection queue as ERCOT-24INR0115 on September 21, 2021. Its proposed commercial operation date is June 1, 2029. The project's interconnection status is currently in the Facility Study phase.
The Aster Solar project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Aster Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7042 Zorn 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HAYSEN1_2
- POI Substation
- Zorn Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.