Utley Solar
221.78 MW generation in Freestone, TX · In queue since September 2021 · Proposed COD May 2028
221.78 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-11
The proposed Utley Solar project is a 221.78 MW solar generation facility in Freestone County, Texas. Developed by Palmera Solar Development LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0117, with a queue entry date of September 7, 2021. The proposed commercial operation date is May 11, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Utley Solar is Tap 345kV 3381 Big Brown Switch - 3391 Jewett. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Palmera Solar Development LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3381 Big Brown Switch - 3391 Jewett
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Utley Solar