Eytcheson Ranches Solar
76.42 MW generation in Navarro, TX · In queue since September 2021 · Proposed COD January 2028
76.42 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
Eytcheson Ranches Solar is a proposed solar generation project located in Navarro County, Texas, with a total capacity of 76.42 MW. The project, developed by Gransolar Texas Fourteen, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0120. It entered the interconnection queue on September 14, 2021, and has a proposed commercial operation date of January 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Eytcheson Solar operating plant (EIA ID 66398). The point of interconnection is Tap 69kV 186 Navarro Mills _x0013_ 107 Prairie Hill. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Fourteen, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV 186 Navarro Mills _x0013_ 107 Prairie Hill
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
- POI Substation
- Limestone Wind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Eytcheson Ranches Solar