PHOTO BESS 2
150 MW storage in Uvalde, TX · In queue since October 2021 · Proposed COD September 2027
150 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
PHOTO BESS 2 is a proposed 150 MW battery storage project located in Uvalde County, Texas. The project, developed by CED Development Inc., is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-24INR0122 on October 29, 2021. The proposed commercial operation date is September 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The development project consists of 150 MW of battery storage capacity. Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
TX
County
Uvalde
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5885 Downie 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HELIOS_RN
- POI Substation
- Downie Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26