High Noon Solar
182 MW generation in Hill, TX · In queue since November 2021 · Proposed COD May 2028
182 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
2y 6m
IA → COD
4 years
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-09
High Noon Solar is a proposed 182 MW solar generation project located in Hill County, Texas. The developer is High Noon Solar Project, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0124, with a queue entry date of November 3, 2021, and a proposed commercial operation date of May 9, 2028. The project's Interconnection Agreement (IA) was executed on May 3, 2024.
The High Noon Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
High Noon Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 445 Yates - 444 Covington
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about High Noon Solar