Grasshopper Solar
407.68 MW generation in Haskell, TX · In queue since September 2021 · Proposed COD October 2028
407.68 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Grasshopper Solar project is a proposed 407.68 MW solar generation facility in Haskell County, Texas. Developed by Grasshopper Solar LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0125, with a queue entry date of September 28, 2021. The proposed commercial operation date is October 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection is the Smoky Hill 345kV Substation. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Grasshopper Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Smoky Hill 345kV Sub (Bus #6104) Locational coordinates : 33.34414; 99.624637
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.