Naduah Solar
102.3 MW generation in Limestone, TX · In queue since September 2021 · Proposed COD October 2027
102.3 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-15
The Naduah Solar project is a proposed 102.3 MW solar generation facility in Limestone County, Texas. Developed by Gransolar Texas Fifteen, LLC, the project entered the ERCOT interconnection queue as ERCOT-24INR0127 on September 27, 2021. Its proposed commercial operation date is October 15, 2027, and its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Naduah Solar operating plant (EIA ID 66396). Recent news coverage of the project has appeared, primarily related to deals.
Generated from interconnection queue and public data sources
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Fifteen, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV Ben Hur (99) - Prairie Hill (107)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Ben Hur Substation