Desna BESS (ERCOT-24INR0128) — Project Summary

Queue ID
ERCOT-24INR0128
Capacity
205.46 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
BRP Desna BESS LLC
IA Status
IA Executed

Desna BESS

ERCOT-24INR0128BetaActiveBatteryERCOTLBNL + Live

205.46 MW storage in Brazoria, TX · In queue since December 2021 · Proposed COD May 2026

205.46 MW

Capacity

1

Components

Battery

4y 5m

In Queue

IA Executed

IA Status

Signed Sep 2023

Interconnection

Queue → IA

1y 9m

IA → COD

2y 8m

Total Duration

1y 9m

Construction75%
Queue EntryDec 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 15, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-05-06

About

The Desna BESS project is a proposed 205.46 MW battery storage project located in Brazoria County, Texas. Developed by BRP Desna BESS LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0128. The project entered the interconnection queue on December 15, 2021, and has a proposed commercial operation date of May 6, 2026.

The project's Interconnection Agreement (IA) has been executed as of September 15, 2023. The Desna BESS project is linked to the existing Desna operating plant (EIA ID 65876). The point of interconnection is the 39703 TNP FM524 138kV. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Desna BESS LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

39703 TNP FM524 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
SCLP_PUN1
POI Substation
FM 524 Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Desna BESS