Eagle Springs Storage
55.1 MW storage in Delta, TX · In queue since October 2021 · Proposed COD December 2026
55.1 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Eagle Springs Storage is a proposed 55.1 MW battery storage project located in Delta County, Texas. The project, developed by Eagle Springs Solar, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-24INR0136, with a queue entry date of October 18, 2021. The proposed commercial operation date is December 31, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The Eagle Springs Storage project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Delta
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eagle Springs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Lake Creek Substation (#6835) _x0013_ Enloe Switching station (#6834) 138 kV Line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SCES_UNIT1
- POI Substation
- Lake Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Eagle Springs Storage