Gaia Storage
76.83 MW storage in Navarro, TX · In queue since December 2021 · Proposed COD May 2026
76.83 MW
Capacity
1
Components
Battery
4y 5m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 11m
IA → COD
2y 6m
Total Duration
1y 11m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
The Gaia Storage project is a proposed 76.83 MW battery storage project located in Navarro County, Texas. The developer is Gaia Solar, LLC. This project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0140, with a queue entry date of December 29, 2021, and a proposed commercial operation date of May 1, 2026.
The project's Interconnection Agreement (IA) has been executed as of November 8, 2023. The point of interconnection (POI) is at Tap 138kV 3127 Trinidad SES - 3454 Montfort Switch.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gaia Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3127 Trinidad SES - 3454 Montfort Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TRSES_UNIT6
- POI Substation
- Trinidad Substation