Lupinus Solar 1
164.86 MW generation in Franklin, TX · In queue since December 2021 · Proposed COD September 2027
164.86 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-13
Lupinus Solar 1 is a proposed solar generation project with a total capacity of 164.86 MW. The project, located in Franklin County, Texas, is being developed by Lupinus Solar, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0150, with a queue entry date of December 8, 2021, and a proposed commercial operation date of September 13, 2027. The project's interconnection status is currently in the Facility Study phase.
The development project has been featured in recent news coverage related to deals and development.
Generated from interconnection queue and public data sources
State
TX
County
Franklin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lupinus Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 11699 Woodard Switch - 1695 Monticello SES
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lupinus Solar 1