Merope BESS
401.92 MW storage in Comanche, TX · In queue since December 2021 · Proposed COD March 2028
401.92 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Merope BESS project is a proposed 401.92 MW battery storage project located in Comanche County, Texas. The developer is BRP Merope BESS LLC. It is interconnected within the ERCOT region, queue ID ERCOT-24INR0157, having entered the queue on December 20, 2021. The proposed commercial operation date is March 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists solely of battery storage, with a total capacity of 401.92 MW. Recent news coverage indicates public interest in the development. The point of interconnection is the 345 kV Corn Trail Switch Substation (#11441).
Generated from interconnection queue and public data sources
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Merope BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Corn Trail Switch Substation (#11441)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Substation 41
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.