Huisache Solar (ERCOT-24INR0160) — Project Summary

Queue ID
ERCOT-24INR0160
Capacity
125.59 MW
Technology
Solar
Status
active
Location
Wilson, TX
Region
ERCOT
Developer
Huisache Solar, LLC
IA Status
Facility Study

Huisache Solar

ERCOT-24INR0160BetaActiveSolarERCOTLBNL + Live

125.59 MW generation in Wilson, TX · In queue since December 2021 · Proposed COD June 2029

125.59 MW

Capacity

1

Components

Solar

4y 5m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection

Total Duration

7y 6m

Facilities Study50%
Queue EntryDec 3, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-30

About

Huisache Solar is a proposed solar generation project located in Wilson County, Texas, within the ERCOT region. The project, developed by Huisache Solar, LLC, has a total capacity of 125.59 MW. It consists entirely of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0160, with an original queue entry date of December 3, 2021. The proposed commercial operation date is June 30, 2029. Its interconnection status is currently in the Facility Study phase. The point of interconnection is planned to tap the Elm Creek to Shaula circuit 1.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wilson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Huisache Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tapping the Elm Creek to Shaula circuit 1

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Huisache Solar