OCI SunRoper (ERCOT-24INR0167) — Project Summary

Queue ID
ERCOT-24INR0167
Capacity
265.1 MW
Technology
Solar
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
OCI SunRoper LLC
IA Status
Facility Study

OCI SunRoper

ERCOT-24INR0167BetaActiveSolarERCOTLBNL + Live

265.1 MW generation in Wharton, TX · In queue since November 2021 · Proposed COD October 2027

265.1 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

5y 11m

Facilities Study50%
Queue EntryNov 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-01

About

The OCI SunRoper project is a proposed solar generation project located in Wharton County, Texas, with a total capacity of 265.1 MW. The developer is OCI SunRoper LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0167, with a queue entry date of November 24, 2021, and a proposed commercial operation date of October 1, 2027. The project's interconnection agreement status is currently in the Facility Study phase.

The proposed project is linked to the existing OCI SunRoper operating plant (EIA ID 65893). The OCI SunRoper project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

OCI SunRoper LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap138kV #43190 South Lane City to #42985 Dyann CKT#60

Data Source

LBNL + Live

DeveloperOCI Energy±pv magazine USA · 2026-03-16
TransactionProject financingpv magazine USA · 2026-03-16
Deal value$394.0Mpv magazine USA · 2026-03-16
LenderING Capital±pv magazine USA · 2026-03-16
PPA structurePhysicalpv magazine USA · 2026-03-16
PPA term20 yearspv magazine USA · 2026-03-16
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW
POI Substation
South Lane City Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-14

View all articles

No ask pi reports yet for this entity.

ask pi about OCI SunRoper