Tejano Storage
152 MW storage in Victoria, TX · In queue since March 2022 · Proposed COD July 2029
152 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
Tejano Storage, LLC is proposing a 152 MW battery storage project called Tejano Storage in Victoria County, Texas. The project is located within the ERCOT region and entered the ERCOT interconnection queue as entry ERCOT-24INR0168 on March 30, 2022. The proposed commercial operation date is July 1, 2029. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 152 MW of battery storage capacity. Recent news coverage indicates industry interest in the Tejano Storage development.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tejano Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8125 Lolita - 8172 Victoria
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Lolita Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.