Bynum Solar Project
56.3 MW generation in Coryell, TX · In queue since December 2021 · Proposed COD May 2026
56.3 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 11m
IA → COD
2y 6m
Total Duration
1y 11m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-05-01
The Bynum Solar Project is a proposed 56.3 MW solar generation project located in Coryell County, Texas. Developed by Bynum Solar Project, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0181, with a queue entry date of December 18, 2021. The proposed commercial operation date is May 1, 2026.
The project's Interconnection Agreement (IA) has been executed as of November 22, 2023. The Point of Interconnection (POI) is Tap 69kV 37470 Olsen - 37520 Sycamore.
Generated from interconnection queue and public data sources
State
TX
County
Coryell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bynum Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 69kV 37470 Olsen - 37520 Sycamore
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DILEOS_UNIT1
- POI Substation
- Olsen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bynum Solar Project