DeSpain Solar Project
236.17 MW generation in Kinney, TX · In queue since December 2021 · Proposed COD December 2027
236.17 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
The DeSpain Solar Project is a proposed 236.17 MW solar generation project located in Kinney County, Texas. The developer is Gransolar Texas Thirteen LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0182, with a queue entry date of December 5, 2021, and a proposed commercial operation date of December 15, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Despain Solar operating plant (EIA ID 66421). The DeSpain Solar Project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Thirteen LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7425 Odlaw Switch 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Odlaw Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about DeSpain Solar Project