Two Forks BESS
309.8 MW storage in Cooke, TX · In queue since January 2022 · Proposed COD June 2027
309.8 MW
Capacity
1
Components
Battery
4y 4m
In Queue
IA Executed
IA Status
Signed May 2024
Queue → IA
2y 4m
IA → COD
3y 1m
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-06-30
Two Forks BESS is a proposed 309.8 MW battery storage project in Cooke County, Texas. Developed by Two Forks LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-24INR0198. The project entered the interconnection queue on January 28, 2022, and has a proposed commercial operation date of June 30, 2027.
The project's Interconnection Agreement (IA) was executed on May 3, 2024. The point of interconnection (POI) is the 684 SPRING 138kV. The development has been mentioned in recent news coverage related to the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Two Forks LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
684 SPRING 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26