Short Creek Solar (ERCOT-24INR0201) — Project Summary

Queue ID
ERCOT-24INR0201
Capacity
625 MW
Technology
Solar
Status
active
Location
Wichita, TX
Region
ERCOT
Developer
Wichita Solar I, LLC
IA Status
IA Executed

Short Creek Solar

ERCOT-24INR0201BetaActiveSolarERCOTLBNL + Live

625 MW generation in Wichita, TX · In queue since January 2022 · Proposed COD December 2027

625 MW

Capacity

1

Components

Solar

4y 4m

In Queue

IA Executed

IA Status

Signed Oct 2024

Status
as of 2 years ago
Latest milestonecommercial operation · 2025-05-02pv magazine USA · 2024-05-06
Interconnection

Queue → IA

2y 9m

IA → COD

3y 2m

Total Duration

2y 9m

Construction75%
Queue EntryJan 20, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 2, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-17

About

Short Creek Solar is a proposed 625 MW solar generation project located in Wichita County, Texas. The developer is Wichita Solar I, LLC. The project is interconnected within the ERCOT queue as entry ERCOT-24INR0201, with a queue entry date of January 20, 2022, and a proposed commercial operation date of December 17, 2027. The interconnection agreement (IA) has been executed as of October 2, 2024.

The proposed project is linked to the existing Short Creek Solar operating plant (EIA ID 68479). Recent news coverage indicates activity related to deals involving the project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Wichita

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Wichita Solar I, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 6101 Riley - 1425 Fisher Road Switch

Data Source

LBNL + Live

DeveloperHexagon Energy±Energies Media · 2026-03-09
TransactionAcquisitionEnergies Media · 2026-03-09
OfftakerTerraForm PowerEnergies Media · 2026-03-09
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-04-09

View all articles