Trigo Solar Project
145.62 MW generation in La Salle, TX · In queue since January 2022 · Proposed COD December 2025
145.62 MW
Capacity
1
Components
Solar
4y 4m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-15
The Trigo Solar Project is a proposed 145.62 MW solar generation project located in La Salle County, Texas. Developed by Ignis TX Solar Two LLC, the project consists of 145.62 MW of solar photovoltaic generation. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0204, with a queue entry date of January 7, 2022.
The proposed commercial operation date for the Trigo Solar Project is December 15, 2025. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the 5705 Fowlerton 138kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ignis TX Solar Two LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5705 Fowlerton 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Fowlerton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.