Glasgow Storage
101 MW storage in Navarro, TX · In queue since February 2022 · Proposed COD March 2028
101 MW
Capacity
1
Components
Battery
4y 3m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 9m
IA → COD
4y 4m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2028-03-16
The Glasgow Storage project is a proposed 101 MW battery energy storage system in Navarro County, Texas. The project, developed by Glasgow Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0207, with a queue entry date of February 21, 2022.
The project has an executed Interconnection Agreement (IA) as of November 8, 2023, and is proposing a commercial operation date of March 16, 2028. The point of interconnection is on the 345kV line between BUS #2466 Big Onion to #68091 Navarro circuit.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Glasgow Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV line between BUS #2466 Big Onion to #68091 Navarro circuit
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.