Eastbell Milam Solar II
150.6 MW generation in Milam, TX · In queue since March 2022 · Proposed COD November 2025
150.6 MW
Capacity
1
Components
Solar
4y 2m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
1y 7m
IA → COD
2y 1m
Total Duration
1y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-27
Eastbell Milam Solar II is a proposed solar generation project located in Milam County, Texas, with a total capacity of 150.6 MW. The developer is Cattlemen Solar Park II LLC. The project is interconnected within the ERCOT region and carries the queue ID ERCOT-24INR0208. It entered the interconnection queue on March 7, 2022, and has a proposed commercial operation date of November 27, 2025.
The project's Interconnection Agreement (IA) has been executed as of October 25, 2023. The point of interconnection (POI) is the 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2.
Generated from interconnection queue and public data sources
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cattlemen Solar Park II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.