Owens Solar
203.5 MW generation in Bosque, TX · In queue since February 2022 · Proposed COD December 2025
203.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
Owens Solar is a proposed 203.5 MW solar generation project located in Bosque County, Texas. The project, developed by Owens Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0213, with a queue entry date of February 7, 2022. The proposed commercial operation date is December 31, 2025. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for Owens Solar is on the 138kV line between the 177 BOSQUE and 181 Cayote substations. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bosque
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Owens Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV line between 177 BOSQUE and 181 Cayote
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Owens Solar