St. Gall Solar
207 MW generation in Pecos, TX · In queue since February 2022 · Proposed COD June 2026
207 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The St. Gall Solar project is a proposed 207 MW solar generation facility in Pecos County, Texas. The project, developed by St. Gall Solar LLC, is located within the ERCOT region and entered the interconnection queue as ERCOT-24INR0233 on February 28, 2022. The proposed commercial operation date is June 1, 2026, and the project's interconnection status is currently in the Facility Study phase.
The St. Gall Solar project has been the subject of recent news coverage, with six articles appearing in industry and grid-related publications.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
St. Gall Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38355 Leon Creek 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LEONLCPCT1_2
- POI Substation
- Leon Creek Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about St. Gall Solar