Bayside BESS
507.8 MW storage in Victoria, TX
507.8 MW
Capacity
1
Components
Battery
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Bayside BESS project is a proposed 507.8 MW battery storage project located in Victoria County, Texas. The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0237. As of the latest data, the project's status is listed as suspended.
The development project consists entirely of battery storage, with a total capacity of 507.8 MW. The entity associated with the project is ERCOT.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.