Pruett Solar
150.54 MW generation in Wise, TX · In queue since February 2022 · Proposed COD May 2027
150.54 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-25
The Pruett Solar project is a proposed 150.54 MW solar generation facility in Wise County, Texas. The project, developed by Crandall Solar LLC, is located within the ERCOT region and interconnected to the grid at Tap 138kV 587 Greenwood - 685 Leo. It entered the ERCOT interconnection queue as queue ID ERCOT-24INR0257 on February 28, 2022, and has a proposed commercial operation date of May 25, 2027. The project's interconnection status is currently in the Facility Study phase.
The Pruett Solar project has been the subject of recent news coverage, with two articles appearing in industry and deals publications.
Generated from interconnection queue and public data sources
State
TX
County
Wise
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Crandall Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 587 Greenwood - 685 Leo
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Greenwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.