Zeissel Solar (ERCOT-24INR0258) — Project Summary

Queue ID
ERCOT-24INR0258
Capacity
457.5 MW
Technology
Solar
Status
active
Location
Knox, TX
Region
ERCOT
Developer
ZSS Power, LLC
IA Status
IA Executed

Zeissel Solar

ERCOT-24INR0258BetaActiveSolarERCOTLBNL + Live

457.5 MW generation in Knox, TX · In queue since February 2022 · Proposed COD June 2028

457.5 MW

Capacity

1

Components

Solar

4y 3m

In Queue

IA Executed

IA Status

Signed Feb 2024

Interconnection

Queue → IA

2 years

IA → COD

4y 4m

Total Duration

2 years

Construction75%
Queue EntryFeb 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 24, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-06-30

About

The Zeissel Solar project is a proposed 457.5 MW solar generation facility in Knox County, Texas. The project, developed by ZSS Power, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0258, with a queue entry date of February 28, 2022. The proposed commercial operation date is June 30, 2028.

The project's interconnection agreement was executed on February 24, 2024. The point of interconnection is the 60700 Gauss 345 KV substation. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Knox

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ZSS Power, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60700 Gauss 345 KV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Gauss Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.