Red Egret BESS
310.58 MW storage in Galveston, TX · In queue since March 2022 · Proposed COD August 2026
310.58 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
1y 3m
IA → COD
3y 2m
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-08-31
The Red Egret BESS project is a proposed 310.58 MW battery storage project located in Galveston County, Texas. The developer is Red Egret LLC. It is interconnected within the ERCOT region under queue ID ERCOT-24INR0281.
The project entered the interconnection queue on March 14, 2022, with a proposed commercial operation date of August 31, 2026. The Interconnection Agreement (IA) for the project has been executed as of June 7, 2023. The Point of Interconnection (POI) is the 38820 FREEWAY PARK 138KV.
Generated from interconnection queue and public data sources
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Red Egret LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38820 FREEWAY PARK 138KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TOPAZ_ALL
- POI Substation
- Freeway Park Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.