Sunshine Solar
130.72 MW generation in Victoria, TX · In queue since September 2022 · Proposed COD December 2026
130.72 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
Sunshine Solar is a proposed 130.72 MW solar generation project located in Victoria County, Texas. The project, developed by Sunshine Energy LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0283, with a queue entry date of September 2, 2022. The proposed commercial operation date is December 1, 2026. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 130.72 MW of solar photovoltaic generation. It is planned to interconnect at a tap on the 138kV Lolita (#8125) - Victoria (#8172) Line. The project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sunshine Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap on the 138kV Lolita (#8125) - Victoria (#8172) Line
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26