APV Plumwood Storage
200.82 MW storage in Chambers, TX · In queue since March 2022 · Proposed COD May 2027
200.82 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
Signed Sep 2024
Queue → IA
2y 6m
IA → COD
2y 8m
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-05-01
APV Plumwood Storage is a proposed 200.82 MW battery storage project located in Chambers County, Texas. The project is being developed by APV Lonestar Energy LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-24INR0285, with a queue entry date of March 30, 2022.
The proposed commercial operation date is May 1, 2027. The project's Interconnection Agreement (IA) has been executed as of September 3, 2024. The point of interconnection is Tap 138kV 40171 Baytown - 40015Cedar Bayou Plant.
Generated from interconnection queue and public data sources
State
TX
County
Chambers
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
APV Lonestar Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 40171 Baytown - 40015Cedar Bayou Plant
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- EXN_1_3
- POI Substation
- Baytown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about APV Plumwood Storage