Rockridge Solar Project
221.27 MW generation in Guadalupe, TX · In queue since April 2022 · Proposed COD April 2027
221.27 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-03
The Rockridge Solar Project is a proposed solar generation project located in Guadalupe County, Texas. Developed by Magnolia Solar Development LLC, the project has a total capacity of 221.27 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0287, with a queue entry date of April 18, 2022, and a proposed commercial operation date of April 3, 2027. Its interconnection status is currently in the Facility Study phase. The Rockridge Solar Project has been mentioned in recent news coverage related to industry and deals.
Generated from interconnection queue and public data sources
State
TX
County
Guadalupe
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Magnolia Solar Development LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7225 Hickory Forest 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Hickory Forest Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rockridge Solar Project