Ratcliff Solar
85.74 MW generation in Freestone, TX · In queue since June 2022 · Proposed COD April 2029
85.74 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-07
Ratcliff Solar is a proposed 85.74 MW solar generation project located in Freestone County, Texas. The project, developed by Greenalia Solar Power Ratcliff, is interconnected within the ERCOT region under queue ID ERCOT-24INR0289. It entered the interconnection queue on June 27, 2022, and has a proposed commercial operation date of April 7, 2029. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Ratcliff Solar Park operating plant (EIA ID 67563). Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
TX
County
Freestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenalia Solar Power Ratcliff
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3279 Long Lake Tap Switch - 3280 Long Lake
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FREC_CC1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.