Citrus Flatts BESS
100.8 MW storage in Cameron, TX · In queue since March 2022 · Proposed COD May 2026
100.8 MW
Capacity
1
Components
Battery
4y 2m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
1y 6m
IA → COD
2y 8m
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-16
Citrus Flatts BESS is a proposed 100.8 MW battery storage project in Cameron County, Texas. Developed by Citrus Flatts Energy Center, LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0294, with a queue entry date of March 30, 2022, and a proposed commercial operation date of May 16, 2026.
The project has an executed Interconnection Agreement (IA), signed on September 8, 2023. The Point of Interconnection (POI) is the 80022 Oleander 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Citrus Flatts Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80022 Oleander 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HARLIN_1_RN
- POI Substation
- Oleander Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Citrus Flatts BESS